Status: Granted
Application Details
Description
Upgrade the existing supply from single phase to three phase. Replacing the existing conductor(s) to that of the type required for the works. Increase the capacity from split-phase (2 wire) to Three-Phase (3 wire). In addition to this, the capacity of the existing pole-mounted transformer (PMT) shall be increased to 200 kVA upon a H Pole as opposed to the single wood pole.
Council
Wiltshire
Application Type
Section 37 Notification - Overhead Lines Electricity Act
Date Validated
11 Nov 2025
Council Website
View on Wiltshire websiteLocation
Coordinates
51.338929920892184, -2.129732440410143
Source: Lat and Lng
Quick Info
- UID
- PL/2025/08948
- Reference
- PL/2025/08948
- Status
- Granted
- Last Updated
- 23 Jan 2026