2025/0361/FUL
Status: Pending
Application Details
Description
Construction and operation of a 50MW battery energy storage system (BESS) facility including the erection of battery container units, inverters, 132kV substation, 33kV customer switchgear, storage container and welfare container, water tank, new internal access roads, resurfaced compound, installation of perimeter fencing and access gate, associated works; and landscaping
Council
Wigan
Application Type
Neighbouring LA
Date Received
30 Oct 2025
Date Validated
30 Oct 2025
Council Website
View on Wigan websiteLocation
Address
Land South West Of New Fold Orrell
Quick Info
- UID
- A/25/099954/NLA
- Reference
- 2025/0361/FUL
- Status
- Pending
- Last Updated
- 07 Mar 2026