UPRN 10094819353

Unique Property Reference Number

Property Information
UPRN

10094819353

Connected Address

Development At Builders Yard And Land At, Station Approach, Barkingside, Ilford

From planning application records

Planning Applications
Council Reference Date Status Description
Redbridge 0056/25/04 04 Jul 2025 Granted Discharge of conditions for approved permission 0056/25: Blue Badge Car Parking Management Plan (Condition 24) …
Redbridge 0056/25/02 10 May 2025 Granted Discharge of conditions for approved permission 0056/25: Landscape Management Plan (Condition 12). (Summary).
Redbridge 0056/25/03 10 May 2025 Granted Discharge of conditions for approved permission 0056/25: Works to Station Approach (Condition 20). (Summary).
Redbridge 0056/25/01 16 Apr 2025 Granted Non-Material Amendment to approved permission 0056/25: External alterations to window heads to remove louvres to …
Redbridge 3417/22/21 06 Mar 2025 Granted Discharge of conditions of approved permission 3417/22: Secured by Design (Condition 16). (summary)
Redbridge 3417/22/22 06 Mar 2025 Granted Discharge of conditions of approved permission 3417/22: CO2 Reduction (Condition 23). (Summary)
Redbridge 3417/22/20 25 Feb 2025 Granted Discharge of conditions for approved permission 3417/22: External lighting (Condition 15). (Summary).
Redbridge 3417/22/19 19 Feb 2025 Granted Discharge of conditions for approved permission 3417/22: Wildlife housing (Condition 21); Habitat Creation Management Plan …
Redbridge 3417/22/18 07 Feb 2025 Granted Discharge of conditions of approved permission 3417/22: Electric vehicle charging Points (EVCP) (Condition 11). (summary)
Redbridge 3417/22/17 05 Feb 2025 Granted Discharge of conditions for approved permission 3417/22: Estate Management Plan (Condition 25). (Summary).
Redbridge 3417/22/16 24 Jan 2025 Granted Discharge of conditions for approved permission 3417/22: Protection of trees (Condition 3). (Summary).
Redbridge 3417/22/15 15 Jan 2025 Granted Discharge of conditions for approved permission 3417/22: Child play areas (Condition 13). (Summary).
Redbridge 3417/22/14 15 Jan 2025 Granted Discharge of conditions for approved permission 3417/22: Facing Materials (Condition 10 (E) and (H)). (Summary).
Redbridge 0056/25 15 Jan 2025 Granted Removal of condition 29 of approved permission 3417/22: Requirement for secondary ventilation is not required …
Redbridge 3417/22/13 10 Jan 2025 Granted Discharge of conditions of approved permission 3417/22: Energy Network (Condition 26). (summary)
Redbridge 3417/22/12 10 Jan 2025 Granted Discharge of Conditions of approved permission 3417/22: Walls and Fences (Condition 14). (summary)
Redbridge 3417/22/11 18 Dec 2024 Granted Non Material Amendment to approved permission 3417/22: Relocation of substation inbetween blocks B and C. …
Redbridge 3417/22/10 04 Oct 2024 Granted Discharge of conditions for approved permission 3417/22: Foul water connection (Condition 19). (Summary).
Redbridge 3417/22/09 04 Sep 2024 Granted Non-material Amendment to approved permission 3417/22: External alterations to include new rainwater outlets, introduction of …
Redbridge 3417/22/08 10 Jul 2024 Granted Discharge of conditions of approved permission 3417/22: - Balustrading (Condition 8). (summary)
Redbridge 1577/24 07 Jun 2024 Withdrawn Removal of Condition 29 of approved planning permission 3417/22: secondary ventilation for cooling purposes is …
Redbridge 3417/22/07 23 Feb 2024 Granted Discharge of conditions of approved permission 3417/22: Facing Materials, (Parts A,B,C,D,F,G) (Condition 10) (summary)
Redbridge 3417/22/06 28 Nov 2023 Granted Discharge of conditions of approved permission 3417/22: Piling (Condition 9). (summary)
Redbridge 3417/22/04 11 Nov 2023 Granted Discharge of conditions of approved permission 3417/22: Decontamination (Part A Condition 7). (summary)
Redbridge 3417/22/03 09 Aug 2023 Granted Discharge of conditions for approved permission 3417/22: Construction management and logistics plan (Condition 5). (Summary).
Redbridge 3417/22/02 27 Jul 2023 Granted Discharge of conditions for approved permission 3417/22: Construction Environmental Management Plan (Condition 6). (Summary).
Statistics
Total Applications
26
Granted
25
Withdrawn
1
First Application
27 Jul 2023
Last Application
04 Jul 2025