UPRN 100052062321

Unique Property Reference Number

Property Information
UPRN

100052062321

Coordinates

53.7564444, -1.2674808

UPRN data version: 2023-05

Connected Address

Sub Station Rawfield Lane Fairburn West Yorkshire

From planning application records

Planning Applications
Council Reference Date Status Description
Selby ZG2025/0554/DORYG 29 May 2025 Unknown Discharge of requirement 10 (1) Replacement Planting for Stage 7.2 of 'The National Grid Yorkshire …
Selby ZG2025/0225/DORYG 27 Feb 2025 Unknown Discharge of requirement 6 (Construction Management Plans), criteria (1) -a) Soil and aftercare management Plan, …
Selby ZG2025/0222/DORYG 26 Feb 2025 Unknown Discharge of requirement 6 (Construction Management Plans), criteria (1) -a) Soil and aftercare management Plan, …
Selby ZG2025/0172/DORYG 17 Feb 2025 Unknown Discharge of Requirement 18 (Approval of Details having regard to the Design Approach to Site …
Selby ZG2024/1311/DORYG 20 Dec 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans) (1) d) -Lighting Management Plan for Stage 5 …
Selby ZG2024/1276/DORYG 10 Dec 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans) (1) c) -Pollution incident Control Plan and f) …
Selby ZG2024/1256/DORYG 04 Dec 2024 Decided and closed Discharge of Requirement 19 (Site Specific Mitigation Scheme for the Travellers Encampment within Work Area …
Selby ZG2024/1186/DORYG 15 Nov 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans) (1) g) -Tree and hedgerow protection strategy and …
Selby ZG2024/1151/DORYG 05 Nov 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans), criteria 6 (1) -a) -Soil and Aftercare Management …
Selby ZG2024/1139/DORYG 31 Oct 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans), criteria 6 (1) -b) -Drainage Management Plan for …
Selby ZG2024/1138/DORYG 31 Oct 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans), criteria 6 (1) -c) -Pollution Incident Control Plan, …
Selby ZG2024/0861/FUL 04 Oct 2024 Granted Formation of concrete pad foundation, installation of steel frames for overhead buss bars and excavation …
Selby ZB24/01936/DORYG 02 Oct 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans) (1) b) -Drainage Management Plan for Sub Stage …
Selby ZG2024/1039/DORYG 30 Sep 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans) 6 (1) a) Soil and Aftercare management Plan …
Selby ZB24/01948/DORYG 25 Sep 2024 Decided and closed Discharge of requirement 6 (Construction Management Plans), criteria (1) -e) -Emergency Response Plan for Flood …
Selby ZG2024/0983/DORYG 13 Sep 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans) 6 (1) b) Drainage Management Plan, 6 1) …
Selby ZB24/01669/DORYG 27 Aug 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans) (1) b) -Drainage Management Plan for Sub Stage …
Selby ZC24/02951/DORYG & ZB24/01670/DORYG 22 Aug 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans) (1) a) -Soil and Aftercare Management Plan for …
Selby ZB24/01666/DORYG 21 Aug 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans) (1) a) -Soil and Aftercare Management Plan for …
Selby ZB24/01690/DORYG 21 Aug 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans) (1) g) -and 9 (1) Tree and Hedgerow …
Selby ZB24/01668/DORYG 21 Aug 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans) (1) c) -Pollution Incidence Control Plan for Sub …
Selby ZB24/01664/DORYG 21 Aug 2024 Decided and closed Discharge of requirement 6 (Construction Management Plans) criteria (1) -f) - Site Waste Management Plan …
Selby ZB24/01665/DORYG 21 Aug 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans) (1) e) -Emergency Response Plan for Flood Events …
Selby ZC24/02767/DORYG & ZB24/01619/DORYG 13 Aug 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans) (1) g) -tree and hedgerow protection strategy and …
Selby ZC24/02611/DORYG & ZB24/01462/DORYG 01 Aug 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans), criteria (1) -d) -Lighting Scheme, for Stage 1.1 …
Selby ZB24/01463/DORYG & ZC24/02590/DORYG 25 Jul 2024 Decided and closed Discharge of Requirement 6 (Construction Management Plans), criteria (1) -c) -Pollution Incidence Control Plan, for …
Selby ZC24/02588/DORYG & ZB24/01458/DORYG 25 Jul 2024 Decided and closed Discharge of requirement 6 (Construction Management Plans), criteria (1) -f) -Site Waste Management Plan, for …
Selby ZC24/02589/DORYG & ZB24/01459/DORYG 25 Jul 2024 Decided and closed Discharge of requirement 6 (Construction Management Plans), criteria (1) -e) -Emergency Response Plan for Flood …
Selby 2023/0018/GOV 04 Jan 2023 Pending Application for Development Consent Order (DCO) under the Planning Act 2008 - Yorkshire Green Energy …
Statistics
Total Applications
29
Granted
1
Pending
1
First Application
04 Jan 2023
Last Application
29 May 2025