Section 37 application consultation relating to the installation of new 400 kv overhead lines and the erection of one new 49m high pylon in association with the proposed development being considered under ref: 23/01502/FUL (Proposed construction a new cable tunnel beneath the River Thames between Tilbury and Gravesend to provide additional transmission capacity. Above-ground infrastructure in the form of a new Cable Sealing End compound and a new head house building along with associated electricity infrastructure, access, parking, boundary treatment and two overhead gantry structures for future overhead lines. Temporary compound for the duration of the project to provide parking, staff welfare facilities, delivery vehicle parking, and equipment and machinery storage, including boundary treatment and lighting).

Council

Thurrock

Application Type

Electric Overhead Lines & Power Stations

Date Received

16 Jan 2024

Date Validated

24 Jan 2024

Location
Address

Land To The South Of National Grids Electrical Substation For New Cable Tunnel Fort Road Tilbury Essex

Coordinates

51.457907128618309, 0.390820741033849

Source: Lat and Lng

Quick Info
UID
24/00057/ELEC
Reference
24/00057/ELEC
Status
Advised
Last Updated
25 Mar 2024