R/2023/0258/CD

Status: Granted (24 Apr 2023)
Application Details
Description

DISCHARGE OF CONDITION 6 (HIGHWAY ACCESSES) OF PLANNING PERMISSION R/2020/0355/FFM FOR STAGE TCPA 1 AND TCPA 6 FOR INSTALLATION OF UNDERGROUND HIGH VOLTAGE ELECTRICAL CABLES AND ANCILLARY WORKS WITHIN FIVE AREAS TO CONNECT EXISTING APPROVED DOGGER BANK C AND SOFIA WIND OFFSHORE WIND FARMS AND LACKENBY SUBSTATION AND ASSOCIATED TEMPORARY CONSTRUCTION COMPOUNDS (NO. NINE), HAUL ROAD, FIVE SITE ACCESSES, CONSTRUCTION OF RETAINING WALL AND REPROFILING OF EXISTING BUND WITH SURPLUS SPOIL

Council

Redcar

Application Type

Condition Discharge

Date Received

30 Mar 2023

Date Validated

30 Mar 2023

Decision Date

24 Apr 2023

Council Website
View on Redcar website
Location
Address

LAND ALONG THE DOGGER BANK C OFFSHORE WIND FARM CABLE CORRIDOR, FROM THE DOGGER BANK C ONSHORE CONVERTER STATION SOUTH OF WILTON INTERNATIONAL UP TO LACKENBY NATIONAL GRID SUBSTATION

Coordinates

54.570056302160850, -1.127385492680694

Source: Application Form

Quick Info
UID
R/2023/0258/CD
Reference
R/2023/0258/CD
Status
Granted
Last Updated
25 Apr 2023