24/0600/PA
Status: Granted
(31 Jan 2025)
Application Details
Description
Construction of a Battery Energy Storage System (BESS) including Battery Containers and Power Conversion Systems; lighting, security fencing, hard and soft landscaping, drainage, vehicle access/circulation, temporary construction laydown areas, ancillary equipment and other associated infrastructure; and an underground electrical cable connection to the National Grid Substation
Council
Pembrokeshire
Application Type
Major (Full)
Date Received
12 Sep 2024
Date Validated
17 Sep 2024
Decision Date
31 Jan 2025
Council Website
View on Pembrokeshire websiteLocation
Address
Land at Entrance To Pembroke Power Station, Pwllcrochan, Pembroke, SA71 5SS
Postcode
SA71 5SS
Coordinates
51.687947262585098, -4.990795536220180
Source: Application Form
Quick Info
- UID
- 41891
- Reference
- 24/0600/PA
- Status
- Granted
- Last Updated
- 11 Feb 2025