1MC09-BBV-TP-APP-NS04_NL12-000002

Status: Granted (14 Oct 2024)
Application Details
Description

Plans and Specifications submission under Schedule 17 to the High Speed Rail (London - West Midlands) Act 2017 for works comprising: Paragraph 2 - Construction of concrete retaining walls, construction of headwalls, wingwalls and handrails associated with Water Orton Culvert and the provision of a cascade. Paragraph 3 - Earthworks to form two parallel railway embankments ('Marsh Lane Embankment'), earthworks to form 3x landscaping bunds, earthworks to form 2x balancing ponds, 8x ecological ponds, drainage ditches and swales, earthworks to form a new public right of way (bridleway), earthworks to form a watercourse diversion, earthworks to form maintenance access tracks, a vehicle access track and areas for road vehicle parking and turning, provision of maintenance access stairs, provision of a track-side noise barrier, and location of permanent fencing.

Council

North Warwickshire

Date Received

09 Feb 2024

Date Validated

13 Feb 2024

Decision Date

14 Oct 2024

Location
Address

HS2 Marsh Lane Embankment Land West Of Junction 8 M42 Motorway Coleshill Road Water Orton

Coordinates

52.510929663310463, -1.732964450520761

Source: Lat and Lng

Quick Info
UID
HS2/2024/0003
Reference
1MC09-BBV-TP-APP-NS04_NL12-000002
Status
Granted
Last Updated
20 Oct 2024