25/P/0969/DCM
Status: Granted
(01 Oct 2025)
Application Details
Description
Formal submission to discharge Requirement 9(1)(d) (Provision of embedded landscape mitigation and landscaping schemes - Towerhead Brook Bridge) for Stage 2.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended)
Council
North Somerset
Date Received
12 May 2025
Date Validated
12 May 2025
Decision Date
01 Oct 2025
Council Website
View on North Somerset websiteLocation
Address
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth
Coordinates
51.413756348486395, -2.820856130189161
Source: Application Form
Quick Info
- UID
- 25/P/0969/DCM
- Reference
- 25/P/0969/DCM
- Status
- Granted
- Last Updated
- 02 Oct 2025