P2024/0064
Status: Granted
(30 Jan 2024)
Application Details
Description
Consultation from the Nationally Significant Infrastructure Project (NSIP) division under Regulations 10 and 11 of The Infrastructure Planning (Environmental Impact Assessment) Regulations 2017 (the EIA Regulations) to inform a Scoping Opinion to construct and operate a new 132 kilovolt (kV) grid connection comprising an overhead line (OHL) supported on L7 steel lattice towers, collector substation and cable sealing end compound (known as the 'Green GEN Vyrnwy Frankton' project)
Council
Neath
Application Type
Scoping Opinion
Date Received
24 Jan 2024
Date Validated
24 Jan 2024
Decision Date
30 Jan 2024
Council Website
View on Neath websiteLocation
Address
Linking Llyn Lort Energy Park In Powys, Wales With Existing 400kV NETS Network In Shropshire, England