P2024/0064

Status: Granted (30 Jan 2024)
Application Details
Description

Consultation from the Nationally Significant Infrastructure Project (NSIP) division under Regulations 10 and 11 of The Infrastructure Planning (Environmental Impact Assessment) Regulations 2017 (the EIA Regulations) to inform a Scoping Opinion to construct and operate a new 132 kilovolt (kV) grid connection comprising an overhead line (OHL) supported on L7 steel lattice towers, collector substation and cable sealing end compound (known as the 'Green GEN Vyrnwy Frankton' project)

Council

Neath

Application Type

Scoping Opinion

Date Received

24 Jan 2024

Date Validated

24 Jan 2024

Decision Date

30 Jan 2024

Council Website
View on Neath website
Location
Address

Linking Llyn Lort Energy Park In Powys, Wales With Existing 400kV NETS Network In Shropshire, England

Quick Info
UID
P2024/0064
Reference
P2024/0064
Status
Granted
Last Updated
23 Jan 2025