Description

Coire Glas Hydro Pumped Storage Scheme - Construction of tunnel, tunnel portal & portal apron (tunnel inclusive of passing places, turning niches & refuge areas) to accommodate installation of 400kV export/import electricity cables to connect Coire Glas generating station to the national grid, including access tracks with surface cable trenching, temporary construction compounds to include but not limited to welfare, parking, plant, materials storage & materials processing, ancillary buildings & spoil storage areas.

Council

Highland

Application Type

Full Application

Date Received

16 Aug 2025

Date Validated

03 Oct 2025

Location
Address

Land 4.4KM SW Of North Laggan Farmhouse North Laggan

Coordinates

57.024314500000000, -4.880748700000000

Source: Application UPRN