Description
Coire Glas Hydro Pumped Storage Scheme - Construction of tunnel, tunnel portal & portal apron (tunnel inclusive of passing places, turning niches & refuge areas) to accommodate installation of 400kV export/import electricity cables to connect Coire Glas generating station to the national grid, including access tracks with surface cable trenching, temporary construction compounds to include but not limited to welfare, parking, plant, materials storage & materials processing, ancillary buildings & spoil storage areas.
Council
Highland
Application Type
Full Application
Date Received
16 Aug 2025
Date Validated
03 Oct 2025
Council Website
View on Highland websiteLocation
Address
Land 4.4KM SW Of North Laggan Farmhouse North Laggan
UPRN
Coordinates
57.024314500000000, -4.880748700000000
Source: Application UPRN