25/01153/S36

Status: Pending
Application Details
Description

Balblair Wind Farm - erection and operation of a wind farm for a period of 30 years, comprising 8 turbines, 2 with maximum blade tip heights of 200m and 6 of 180m along with battery energy storage system (BESS) facility with combined generating capacity of 66MW, access tracks, borrow pits, substation, control building, and ancillary infrastructure. This case will be determined by the Energy Consents Unit. Please visit Energy Consents Unit at https://www.energyconsents.scot/ApplicationSearch.aspx?T=2 using reference number ECU00005055

Council

Highland

Application Type

Section 36

Date Received

14 Mar 2025

Date Validated

14 Mar 2025

Location
Address

Balblair Estate Land 695M NW Of Coirshellach Airdens Bonar Bridge

Coordinates

57.928745300000000, -4.349874600000000

Source: Application UPRN

Quick Info
UID
25/01153/S36
Reference
25/01153/S36
Status
Pending
Last Updated
13 Nov 2025