Description
EIA Screening Opinion for construction and operation of a 132 kiloVolt (kV) single circuit overhead line (OHL) of approximately 8.4 km and approximately 1 km of underground cable (UGC) to connect the proposed Abhainn Dubh Wind Farm to the existing Fyrish Substation
Council
Highland
Application Type
Screening Applications
Date Received
20 Jan 2025
Date Validated
20 Jan 2025
Decision Date
12 Feb 2025
Council Website
View on Highland websiteLocation
Address
Land 140M NW Of 2 Clashnabuiac Alness
UPRN
Coordinates
57.689001346928151, -4.300821983526460