24/05097/S36
Status: Granted
(27 Aug 2025)
Application Details
Description
Knocknagael BESS - Construction and operation of a 200MW Battery Energy Storage System (BESS) comprising two BESS and one substation compounds, associated infrastructure, site access, and landscaping. This case will be determined by the Energy Consents Unit. Please visit Energy Consents Unit at https://www.energyconsents.scot/ApplicationSearch.aspx?T=2 using reference number ECU00005099.
Council
Highland
Application Type
Section 36
Date Received
28 Nov 2024
Date Validated
28 Nov 2024
Decision Date
27 Aug 2025
Council Website
View on Highland websiteLocation
Address
Land 500M South East Of Essich Farm Cottages Inverness
UPRN
Coordinates
57.421723500000000, -4.246796300000000