24/03064/SCOP
Status: Decided and closed
Application Details
Description
Section 37 application for the construction of a new double circuit steel structure 400 kV OHL between Beauly, Blackhillock, New Deer and Peterhead, approximately 194km in length, including the diversion of an existing 400kV OHL into a proposed new Coachford 400kV substation near Blackhillock, removal of the existing 132kV OHL from Beauly to Knocknagael substations, and rationalisation and crossings of the existing transmission network
Council
Highland
Application Type
Scoping Applications
Date Received
08 Jul 2024
Date Validated
08 Jul 2024
Council Website
View on Highland websiteLocation
Address
Land 1525M SE Of Finglack Culloden Moor Inverness
UPRN
Coordinates
57.462675278955778, -4.030874338398859
Source: Lat and Lng
Quick Info
- UID
- 24/03064/SCOP
- Reference
- 24/03064/SCOP
- Status
- Decided and closed
- Last Updated