23/05350/SCOP

Status: Decided and closed (29 Feb 2024)
Application Details
Description

Installation of 132kV overhead line, two cable sealing compounds or two towers, 7.4km underground cable from the proposed Dell Wind Farm on site substation, 1.6 km of 132 kV underground cable from Cloiche Wind Farm on site substation, 0.7 km of 132 kV underground cables on approach into Melgarve substation, access tracks and tree and vegetation clearance, total length of approximately 16.7 km in length (which includes approximately 9.7 km of UGC)

Council

Highland

Application Type

Scoping Applications

Date Received

31 Oct 2023

Date Validated

31 Oct 2023

Decision Date

29 Feb 2024

Location
Address

Land 6900M NW Of SSE Garvamore Laggan

Coordinates

57.083333484616865, -4.507427479358643

Source: Lat and Lng

Quick Info
UID
23/05350/SCOP
Reference
23/05350/SCOP
Status
Decided and closed
Last Updated
05 Oct 2024