H/2023/0341

Status: Decided and closed (23 Oct 2023)
Application Details
Description

Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 (as amended) (the ‘DCO’) Requirement 34 Port Access and Transport Plans for Work Nos. 1B of the offshore works in relation to Sofia Offshore Wind Farm (formerly Teesside B Offshore Wind Farm) (‘Project B’) to reconfirm that a PATP is not required based on a tolerance of 30 vehicles (one PCU)

Council

Hartlepool

Application Type

Adjoining Authority Consultations

Date Received

22 Sep 2023

Date Validated

22 Sep 2023

Decision Date

23 Oct 2023

Location
Address

DOGGER BANK TEESSIDE OFFSHORE WIND FARM HARTLEPOOL

Quick Info
UID
H/2023/0341
Reference
H/2023/0341
Status
Decided and closed
Last Updated
03 Jun 2024