Hampshire - 2024
70 planning applications validated in 2024
70
Total
60
Granted
2
Refused
All Applications
| Reference | Address | Description | Status | Date Validated |
|---|---|---|---|---|
| 25/10023 | Midgham Farm, Near Fordingbridge, Hampshire SP6 3DA | Proposed extraction of sand and gravel with associated access, internal haul roads, processing plant, silt … | Unknown | 23 Dec 2024 |
| CS/25/98704 | Hamble Community Sports College, Satchell Lane Hamble-le-rice, Hampshire SO31 4NE | Recladding of Sydney Block 004X | Granted | 20 Dec 2024 |
| P/25/0016/CC | Waste Transfer Station, Down End Road, Fareham Hampshire PO16 8TR | Installation of a replacement 2 storey office and welfare portacabin | Granted | 16 Dec 2024 |
| EHDC-24-0014-NAC | Whitehouse Farm, Selborne Road, Selborne, Alton GU34 3HL (Cross Boundary … | Demolition of existing farmhouse and construction of new farmhouse and outbuildings | Granted | 16 Dec 2024 |
| 24/02867/CMA | Little Bushywarren Compost Site, Bushywarren, Lane, Ellisfield, Hampshire RG25 2NS | Variation of condition 1 of planning permission 18/03067/CMA (extension of time) | Granted | 06 Dec 2024 |
| 24/02868/CMA | Little Bushywarren Compost Site, Bushywarren Lane, Ellisfield, Hampshire RG25 2NS | Variation of condition 4 of planning permission 18/03073/CMA (extension of time) | Granted | 02 Dec 2024 |
| P/24/1571/CC | Land off Boarhunt Road, Boarhunt Road, Fareham PO17 6AJ | Retrospective Development of an Inert Waste Recycling Facility | Unknown | 22 Nov 2024 |
| - | Bordon Sewage Treatment Works (STW) | EIA Screening Request for Proposed PD Works | Not required | 18 Nov 2024 |
| 24/02682/HCM | Crabwood, Sarum Road, Winchester, Hampshire SO22 5QS | To change the use of land east of Lanham Lane from agricultural land to a … | Granted | 14 Nov 2024 |
| 24/02693/HCM | Denmead Junior School, Bere Road, Denmead Hampshire PO7 6PH | Variation of condition 14 (Plans) of 23/02519/HCS | Granted | 14 Nov 2024 |
| 24/02729/CMA | Little Bushywarren Compost Site, Bushywarren, Lane, Ellisfield, Hampshire RG25 2NS | Variation of Conditions 1 (Life of Site) and 14 (plans) of Planning Permission 18/03065/CMA | Granted | 14 Nov 2024 |
| CS/24/98535 | Luminous Oak SEMH School, Flycatcher Road, Boorley Gardens, Hedge End, … | New two storey school for 125 pupils with Social Emotional and Mental Health (SEMH ) … | Granted | 13 Nov 2024 |
| 24/02611/CMA | Humbly Grove Oilfield, The Avenue, Lasham Hampshire GU34 5SY | Installation of a new oil storage tank at Weston Common, Humbly Grove Oilfield | Granted | 11 Nov 2024 |
| 24/02645/HCM | North Whiteley Secondary School, Dapperling Road, Whiteley | A new build 6 Form Entry (900 pupil), two and three-story purpose-built secondary school serving … | Granted | 08 Nov 2024 |
| 24/02758/HCM | Gas Pipeline, The Avenue, Lasham Hampshire GU34 5SY | Variation of Conditions 26 (Restoration), 2 (Siting, design, external appearance and access to above ground … | Granted | 05 Nov 2024 |
| 24/02254/HCC | Wellsite X, Humbly Grove Oilfield, New Odiham, Road, Alton GU34 … | Variation of Conditions 2 (Retention of plant, buildings, structures, hard standings and haul roads) and … | Granted | 05 Nov 2024 |
| 26326/019 | Humbly Grove Oilfield, The Avenue, Lasham Hampshire GU34 5SY | Variation of Conditions 1 (Exportation of oil by tanker) and 17 (Removal of plant, buildings, … | Granted | 05 Nov 2024 |
| 24/02252/HCC | Humbly Grove Oilfield, The Avenue, Lasham Hampshire GU34 5SY | Variation of Conditions 1 (Exportation of oil by tanker) and 17 (Removal of plant, buildings, … | Granted | 05 Nov 2024 |
| 24/02595/CMA | Humbly Grove Oilfield, The Avenue, Lasham Hampshire GU34 5SY | Variation of Conditions 13 (Noise monitoring scheme) and 15 (Removal of plant, buildings, structures, hard … | Granted | 05 Nov 2024 |
| 24/02643/CMAN | Gas Pipeline, The Avenue, Lasham Hampshire GU34 5SY | Variation of Conditions 26 (Restoration), 2 (Siting, design, external appearance and access to above ground … | Granted | 05 Nov 2024 |
| 24/02597/CMA | Humbly Grove Oilfield, The Avenue, Lasham Hampshire GU34 5SY | Variation of Conditions 1 (Exportation of oil by tanker) and 17 (Removal of plant, buildings, … | Granted | 05 Nov 2024 |
| 24/02599/CMA | Humbly Grove Oilfield, The Avenue, Lasham Hampshire GU34 5SY | Variation of Conditions 2 (Removal of the gas turbine electrical generator units), 3 (Noise suppression … | Granted | 05 Nov 2024 |
| 24/02596/CMA | Humbly Grove Oilfield, The Avenue, Lasham Hampshire GU34 5SY | Variation of Conditions 2 (Hours of working) and 3 (Restoration) of Planning Permission 17/00289/CMA | Granted | 05 Nov 2024 |
| 24/02600/CMA | Humbly Grove Oilfield, The Avenue, Lasham Hampshire GU34 5SY | Variation of Conditions 2 (External materials) and 3 (Cessation of the use and removal of … | Granted | 05 Nov 2024 |
| 24/02610/CMA | Gas Pipeline, The Avenue, Lasham Hampshire GU34 5SY | Variation of Conditions 26 (Restoration), 2 (Siting, design, external appearance and access to above ground … | Granted | 05 Nov 2024 |
| 24/02598/CMA | Humbly Grove Oilfield, The Avenue, Lasham Hampshire GU34 5SY | Variation of Conditions 9 (Removal of plant, buildings, structures, hard standings and haul roads) and … | Granted | 05 Nov 2024 |
| 26326/020 | Gas Pipeline, The Avenue, Lasham Hampshire GU34 5SY | Variation of Conditions 26 (Restoration), 2 (Siting, design, external appearance and access to above ground … | Granted | 05 Nov 2024 |
| 24/11013 | Marchwood Transfer Station, Bury Road, Marchwood SO40 4UD | Variation of Condition 1 of Planning Permission 15/10294 (extend the life of the site) | Granted | 04 Nov 2024 |
| 24/11012 | Marchwood Waste Transfer Station, Bury Road, Marchwood SO40 4SR | Variation of Condition 1 of Planning Permission 17/11019 (extend the life of the site) | Granted | 04 Nov 2024 |
| 24/10957 | Veolia Environmental Services, Integra South West Energy Recovery Facility, Oceanic … | Extension to the Existing Water Intake Building | Granted | 24 Oct 2024 |
| 24/02412/CMAN | The A303 Recycling Facility, Drayton Road, Barton Stacey, Hampshire SO21 … | Variation of condition 2 (Completion Date) of Planning Permission 21/02681/CMAN | Granted | 15 Oct 2024 |
| APP/24/00783 | Sir George Staunton Country Park, Middle Park Way, Havant PO9 … | Structural repairs | Granted | 01 Oct 2024 |
| 24/02041/HCC | The Howf, Bramshot Lane, Fleet | Proposed new build 2 Form Entry (2FE), 420 pupil place, Primary School serving the ‘Hartland … | Granted | 30 Sep 2024 |
| 24/02023/HCS | Land Off, Titchfield Lane, Wickham, Hampshire PO15 6DY | Proposed revised landform modifications to enable the construction of a 10.5 MW Solar Photovoltaic PV_ … | Unknown | 05 Sep 2024 |
| 24/01862/HCS | Silverlake Automotive Recycling, Botley Road, Shedfield, Southampton SO32 2HL | Extension and reconfiguration of Silverlake Garage including; construction of new reverse production line ELV dismantling … | Unknown | 22 Aug 2024 |
| 24/00258/HCCLB | Gosport Museum and Art Gallery, 19 Walpole Road, Gosport Hampshire … | The replacement of failing cavity wall and window and door frame ties and the insertion … | Granted | 02 Aug 2024 |
| 24/01629/HCS | Wickham Wastewater Treatment Works, Tanfield Lane, Wickham, Fareham PO17 5ND | Proposed installation of a Motor Control Centre Kiosk | Granted | 17 Jul 2024 |
| APP/24/00523 | Farlington Redoubt, Portsdown Hill Road, Havant Hampshire PO6 1BW | Application to vary condition 6 & 10 of planning permission APP/15/00757 (to increase the operational … | Granted | 20 Jun 2024 |
| 30633/043 | Grundon Sand and Gravel Ltd Frith End Sand Quarry, Grooms … | Variation of Conditions 1 (Timescale), 4 (Phasing) and 10 (Landscaping) of Planning Permission 30633/040 | Granted | 07 Jun 2024 |
| 30633/044 | Grundon Sand and Gravel Ltd Frith End Sand Quarry, Grooms … | Variation of conditions 1 (Timescale), 3 (Arboriculture), 4 (Phasing), 10, 11 & 25 (Landscaping), 26 … | Granted | 07 Jun 2024 |
| 24/00315/HCC | Aldershot Recycling Facility, Gold Farm, Government Road, Aldershot | Lawful Development Certificate: Use of land as shown on site location plan for the management … | Granted | 22 May 2024 |
| 24/01218/CMAS | Squabb Wood Landfill Site, Salisbury Road, Shootash Hampshire SO51 6GA … | Variation of conditions 1, 2, 3, 10, 11, 13, 14, 19 and 24 of planning … | Granted | 22 May 2024 |
| P/24/0753/CC | Down End Quarry, Down End Road, Fareham Hampshire PO16 8TR | Installation of new building to house a consented shredding operation, a Firetank and Pumphouse | Granted | 20 May 2024 |
| APP/24/00369 | Emsworth House, Emsworth House Close, Emsworth, Hampshire PO10 7JR | Proposed extension to areas of hard surfacing and the installation of a new footpath | Granted | 14 May 2024 |
| P/24/0665/CC | Hollam Hill Farm, Titchfield Road, Titchfield, Fareham Hampshire PO14 3ES | Proposed partial demolition of Barn 003A and retention and weatherboarding of retained eastern end | Granted | 10 May 2024 |
| 24/10425 | Hamer Warren Quarry - Bleak Hill I and II, Harbridge … | Variation of Condition 1, 4, 17, 29, 34 and 46 of Planning Permission 19/11325 to … | Granted | 18 Apr 2024 |
| 24/10405 | Bleak Hill III - Hamer Warren Quarry, Harbridge Drove, Nr … | Variation of planning conditions 2, 5, 27, 31 and 42 of planning permission 19/11326 so … | Granted | 18 Apr 2024 |
| 24/00748/HCC | Eversley Recycling, The Welsh Drive, Eversley Hook Hampshire RG27 0QB … | Phased extraction of approximately 263,000 net tonnes of sand and gravel and 2,553,000 net tonnes … | Unknown | 10 Apr 2024 |
| 24/00723/HCC | Fleet Infants School, Velmead Road, Fleet, Hampshire GU52 7LQ (Listed … | Reroofing of Infant School building | Granted | 09 Apr 2024 |
| APP/24/00290 | The Crookhorn Community School, Stakes Hill Road, Waterlooville, Hampshire PO7 … | Recladding of Goodwood Block | Granted | 09 Apr 2024 |
| CS/24/97256 | Jacksons Farm, Bubb Lane, West End Hampshire SO30 2HL | Change of use from redundant agricultural land to open storage (minerals and waste uses) | Refused | 09 Apr 2024 |
| 24/00807/HCS | Shedfield Equestrian Centre, Lockhams Recycling Ltd, Botley Road, Shedfield Hampshire … | REVISED APPLICATION - Retrospective planning application for the change of use to open storage of … | Refused | 09 Apr 2024 |
| 24/00782/HCC | Bramshill Gas Utilisation Plant (GUP), Plough Lane Eversley | Existing GUP plant. Previous Planning Permission has lapsed | Granted | 05 Apr 2024 |
| 24/00223/HCC | Alderwood Senior School, Tongham Road, Aldershot Hampshire GU12 4AS | The demolition of a teaching block to provide the site for a two-story new build … | Granted | 26 Mar 2024 |
| 24/00736/CMAS | Roke Manor Quarry, Salisbury Road, Shootash, SO51 6GA (EIA) | Variation of Condition 2 (time limits) of Planning Permission 10/02615/CMAS - to extend the time … | Granted | 25 Mar 2024 |
| 24/00739/CMAS | Roke Manor Quarry, Salisbury Road, Shootash, Hampshire SO51 6GA | Variation of Condition 2 (time limits) of Planning Permission 15/00826/CMAS – to extend the time … | Granted | 25 Mar 2024 |
| 24/00703/HCS | Foster Yeoman Ltd, Station Hill, Curdridge, SO30 2DN | Replacement of existing single storey Portacabin with a Double Storey Portacabin | Granted | 22 Mar 2024 |
| 24/00622/CMA | Little Bushywarren Compost Site, Bushywarren Lane, Ellisfield, Hampshire RG25 2NS | Proposed Stand Alone Oil Store (Container) | Granted | 13 Mar 2024 |
| - | Stockbridge County Primary School, Old London Road, Stockbridge, Hampshire SO20 … | Replacement of the school's playfield access gates | Granted | 11 Mar 2024 |
| 24/00794/HCS | Sparsholt C Of E Primary School, Woodman Lane, Sparsholt, Hampshire … | Replacement 3m high chain link fencing around playing field | Granted | 08 Mar 2024 |
| 24/00560/CLB | Basing Grange, Redbridge Lane, Old Basing Hampshire RG24 7HB (LB) | General repairs to the Milking Shed | Granted | 05 Mar 2024 |
| 24/00564/CC3 | Basing Grange, The Street, Old Basing, Hampshire RG24 7BH (Planning) | Carefully dismantling, repairs and reassembly of the lean-too structure roof | Granted | 05 Mar 2024 |
| 24/00484/HCC | Busta Triangle (Eversley Quarry), Cooper's Hill, Eversley Common, Hook Eversley … | The importation of inert materials to deliver a long-term sustainable restoration landform to enable the … | Unknown | 29 Feb 2024 |
| - | A326 (North) Waterside Improvements Scheme, located along the A326 between … | Updated scoping opinion | Decided and closed | 28 Feb 2024 |
| 24/00404/HCS | Henry Beaufort School, Priors Dean Road, Harestock, Hampshire SO22 6JJ | SCOLA reclad of block 007 | Granted | 16 Feb 2024 |
| 24/10155 | Chatsworth Blue Haze Landfill Site, Alderholt Road, Somerley Hampshire BH24 … | Installation of an Incinerator Bottom Ash (IBA) Pad and associated mobile equipment | Granted | 16 Feb 2024 |
| 24/10136 | Slowhill Copse Wastewater Treatment Works, Bury Road, Marchwood SO40 4UD | Construction and operation of a Motor Control Centre (MCC) equipment kiosk | Granted | 09 Feb 2024 |
| APP/24/00131 | Water Treatment Works, Southmoor Lane, Havant Hampshire PO9 1JW | Construction and operation of a Motor Control Centre (MCC) kiosk | Granted | 08 Feb 2024 |
| CS/24/96876 | Netley Household Waste Recycling Centre, Grange Road, Netley SO31 5FF | Variation of condition 1 of planning permission S/14/74104 to extend the time period for a … | Granted | 07 Feb 2024 |
| 24/00121/HCS | The Westgate School, Cheriton Road, Winchester Hampshire SO22 5AZ | Replacement Bin Store including, retaining wall, drainage and hardstanding | Granted | 09 Jan 2024 |