A New Electricity Substation To The North East Of Welborne And A Heat Exchange Energy Centre, Including The Provision Of A Car Park And Access, Associated Hard And Soft Landscaping And Drainage; And The Undergrounding Of The Existing Overhead Electricity Lines (132Kv And 11Kv), The Removal Of Existing Pylons, Erection Of New Terminal Towers And Provision Of Underground Cabling, Site Clearance, Site Compounds And Haul Routes, Ecological Habitat Including Land To Obtain Biodiversity Net-Gain, Nutrient Mitigation, Construction Access, Utility Connections, Engineering Operations And Earthworks.

Council

Fareham

Date Received

19 Jul 2023

Date Validated

16 Aug 2023

Decision Date

11 Jan 2024

Location
Address

Land to the West and East of A32 Associated with Welborne

Quick Info
UID
P/23/1004/FP
Reference
P/23/1004/FP
Status
Granted
Last Updated
12 Jan 2024