EPF/2171/25

Status: Granted (05 Feb 2026)
Application Details
Description

Application to discharge requirement 11 (Stage 1b) – Contaminated Land & Ground Water by National Grid Electricity Transmission plc for an Order Granting Development Consent for the North London Reinforcement Project for the uprating of an existing 275kV transmission line of approximately 14km in length from Waltham Cross substation to Tottenham substation to enable it to run at a voltage of 400kV, together with associated development (Revised application to EPF/0226/25).

Council

Epping Forest

Application Type

Approval of details reserved by a condition

Date Received

22 Oct 2025

Date Validated

22 Oct 2025

Decision Date

05 Feb 2026

Location
Address

Waltham Cross to Tottenham Substation, near to Highbridge Street, Waltham Abbey

Coordinates

51.713894161052153, -0.011406358039157

Source: Application Form