23/0012/PREAPP

Status: Granted (15 Aug 2023)
Application Details
Description

Major Development: Proposed Battery Energy Storage System (BESS) with a capacity of around 29.9MW involving battery containers, a substation and related electrical equipment and associated ancillary infrastructure including new access track, existing access track improvements, surface water drainage/SuDS, perimeter fencing with lighting/CCTV and landscape planting.

Council

East Ayrshire

Application Type

Pre-Application

Date Received

25 Jul 2023

Date Validated

25 Jul 2023

Decision Date

15 Aug 2023

Location
Address

Land South Of Coylton Substation

Quick Info
UID
23/0012/PREAPP
Reference
23/0012/PREAPP
Status
Granted
Last Updated
11 Dec 2023