100649550-001

Status: Granted
Application Details
Description

PROPOSED GRID STABILITY FACILITY COMPRISING FORMATION OF AN ELECTRICAL TRANSMISSION INFRASTRUCTURE COMPOUND CONTAINING TRANSFORMERS, CABLES AND INFRASTRUCTURE, THE ERECTION OF MAIN PLANT ROOM BUILDING, FORMATION OF NEW ACCESS, ANCILLARY CAR PARKING, DRAINAGE, BOUNDARY TREATMENT AND LANDSCAPING AT VARIANCE WITH CONDITION 4 OF PLANNING PERMISSION 20/2071/FUL CONDITION RELATION TO AIL DELIVERIES TO ENABLE AIL DELIVERIES WITHOUT THE NEED FOR A TEST RUN AND TO PROVIDE SUFFICIENT TECHNICAL EVIDENCE TO BE SUBMITTED AND APPROVED IN WRITING INSTEAD

Council

Dumfries

Application Type

Section 42

Date Received

30 Oct 2023

Date Validated

07 Nov 2023

Location
Address

Land East Of Gretna Substation 3km To The North Of Gretna

Coordinates

55.032637695626256, -3.047088933895552

Source: Application Form

Quick Info
UID
23/2331/S42
Reference
100649550-001
Status
Granted
Last Updated
15 Jun 2024