WEB1826/25Sub01

Status: Unknown (04 Dec 2025)
Application Details
Description

4. The following requirements of Drainage Division shall be complied with: (b) The developer shall carry out both a pre- and post-construction CCTV survey on the public surface water sewers affected by this development. The pre-construction survey shall be submitted to the Planning Authority prior to commencement of the development. The post-construction survey shall be submitted for written approval by the planning authority prior to the occupation of the development. Any damage to the sewer shall be rectified at the developer's expense.

Council

Dublin New

Date Validated

24 Oct 2025

Decision Date

04 Dec 2025

Location
Address

46, Belgrove Lawn, Dublin 20, D20 NP80

Quick Info
UID
172362
Reference
WEB1826/25Sub01
Status
Unknown
Last Updated
06 Mar 2026