2. The applicant shall comply with the following drainage requirements of the Planning Authority: II. The management of surface water as indicated on the drawings submitted are not acceptable. The applicant shall submit two revised copies of a detailed site plan to the Planning Authority for written approval. These plans shall be submitted within 3 months of the date of grant. The main points to note in the revised drawings are: SuDS (sustainable drainage systems) measures must be included in the management of surface water.
Council
Dublin New
Date Validated
27 Aug 2025
Decision Date
10 Oct 2025
Council Website
View on Dublin New websiteLocation
Address
23, Coultry Close, Ballumun , Dublin 9