3: The Developer shall comply with the following requirements of the Transportation Planning Division: a) Prior to commencement of development, and on appointment of a main contractor, a Construction Management Plan having regard to mitigation measures as per the Environmental Report (RPS, November 2020) and the Engineering Report (Roughan & O’Donovan, November 2020) shall be submitted to the planning authority for written agreement. This plan shall provide details of intended construction/demolition practice for the development, including traffic management, hours of working, noise and dust management measures and off-site disposal of construction/demolition waste.

Council

Dublin New

Date Validated

09 Feb 2024

Decision Date

25 Mar 2024

Location
Address

At the MTL Terminal on Pigeon House Road, Dublin Port, Dublin 2 and an area to the south of Terminal 5 adjacent to Berth 53, Alexandra Road Extension, Dublin Port, Dublin 1.

Coordinates

53.341691714521367, -6.211000661533078

Source: Lat and Lng

Quick Info
UID
158368
Reference
3748/20Sub01
Status
Decided and closed
Last Updated
03 Nov 2024