PA26/01496
Application Details
Description
National Grid are proposing to upgrade an existing overhead line between poles 43H85 to 43HJ15 and 43HJ15 to 43HJA5 near Penlan Services, Four Winds, Bodmin, Cornwall, PL30 4HH and as per the plans attached. These works are necessary to make the electricity network 3 phase compatible which will provide customers with 3 phase connection to our distribution network. The overhead line route is approximately 1.7 kilometres in length and the main scope of the works will be to install a 3rd wire with the necessary additional fixtures and fittings to support the new line. The new line will attach to insulators on the cross arms of the existing poles and will be in between the two existing outer wires meaning that the visual impact of this additional 3rd wire is considered very minimal. This section of line was refurbished several years ago so it is anticipated that most of the poles will not require any changes however our team will inspect each pole before works commence and if any poles are identified to require replacement this will be done on a like for like basis with the landowners consent and ensuring the old apparatus is dismantled and removed from site. On pole 43HJ15 it will require an out of balance stay to be added to it, this is to keep the pole upright and balanced once the additional wire is installed. I have attached a street view plan showing the works area extents and a network plan showing the line to be included in these works all highlighted yellow
Council
Cornwall
Application Type
Overhead Electricity Lines
Date Validated
04 Mar 2026
Decision Date
09 Apr 2026
Council Website
View on Cornwall websiteLocation
Address
Near Penlan Services Blisland Bodmin Cornwall PL30 4HH
Postcode
PL30 4HH
Coordinates
50.509806767434860, -4.662708287783577
Source: Lat and Lng
Quick Info
- UID
- PA26/01496
- Reference
- PA26/01496
- Status
- Granted
- Last Updated
- 12 Apr 2026