SPD/2026/0010/PAN

Status: Granted (26 Jun 2026)
Application Details
Description

The Repower of the existing Altahullion Phase I & II wind farm (s) comprising the following main components; (i) Decommissioning of the existing 29 No. turbines (ii) Removal and restoration of the existing substation building and compound (iii) Removal and restoration of the other redundant infrastructure (iv) erection of 8 No. wind turbines with an output of approximately 48MW (v) Construction of new of access tracks; (vi) Upgrade of existing access tracks; (vii) Construction of temporary and permanent hardstanding areas for each turbine to accommodate turbine component laydown areas, crane hardstanding areas and external transformers and/or switchgears; (viii) temporary construction compound/laydown area; (ix) Turning heads and passing places incorporated within the site access infrastructure; (x) control building and substation compound; (xi) During construction and commissioning there would be a number of temporary works including a construction compound with car parking; temporary parts of crane hardstandings; welfare facilities.

Council

Causeway Glens

Application Type

Proposal of Application Notice

Date Received

28 May 2026

Date Validated

28 May 2026

Decision Date

26 Jun 2026

Location
Address

Existing Altahullion I & II Wind Farm (s), located in the townlands of Drum & Glenconway, Limavady, Co Derry/Londonderry which is located 3km north of Foreglen in Derry/Londonderry.

Coordinates

54.961092836487914, -7.030901581247172

Source: Lat and Lng

Quick Info
UID
711341
Reference
SPD/2026/0010/PAN
Status
Granted
Last Updated
21 Jul 2026