3DC/2023/0273/DCO

Status: Granted (17 Nov 2023)
Application Details
Description

Discharge of Requirements 24 and 28 of The Norfolk Boreas Offshore Wind Farm Order 2021, as amended by The Norfolk Boreas Offshore Wind Farm (Amendment) Order 2022, for Stage 7 the 400kV Connections Works.

Council

Breckland New

Application Type

Dev Consent Order

Date Received

06 Oct 2023

Date Validated

06 Oct 2023

Decision Date

17 Nov 2023

Location
Address

400kV Connections Works adjacent to the Necton National Grid

Coordinates

52.661042100888203, 0.790059146642098

Source: Application Form