3DC/2023/0271/DCO

Status: Granted (01 Dec 2023)
Application Details
Description

Discharge of Requirement 25 (Watercourse Crossing Scheme) of The Norfolk Boreas Offshore Wind Farm Order 2021, as amended by The Norfolk Boreas Offshore Wind Farm Order 2022 (Amendment), for Stage 7 400kV Connections Works

Council

Breckland New

Application Type

Dev Consent Order

Date Received

06 Oct 2023

Date Validated

06 Oct 2023

Decision Date

01 Dec 2023

Location
Address

400kV Connections Works adjacent to the Necton National Grid

Coordinates

52.661042100888203, 0.790059146642098

Source: Application Form

Quick Info
UID
3DC/2023/0271/DCO
Reference
3DC/2023/0271/DCO
Status
Granted
Last Updated
04 Dec 2023