3DC/2023/0211/DCO
Status: Granted
(16 Nov 2023)
Application Details
Description
Discharge of Requirement 23 (Archaeological Written Scheme of Investigation) of The Norfolk Boreas Offshore Wind Farm Order 2021, as amended by The Norfolk Boreas Offshore Wind Farm (Amendment) Order 2022, for Stage 3 Onshore Project Substation Enabling Works (Work No. 8A & 8B).
Council
Breckland New
Application Type
Dev Consent Order
Date Received
04 Aug 2023
Date Validated
04 Aug 2023
Decision Date
16 Nov 2023
Council Website
View on Breckland New websiteLocation
Address
Onshore Project Substation
Coordinates
52.658122400519602, 0.808580613583405
Source: Application Form
Quick Info
- UID
- 3DC/2023/0211/DCO
- Reference
- 3DC/2023/0211/DCO
- Status
- Granted
- Last Updated
- 18 Nov 2023