23/00801/FUL

Status: Granted (26 Oct 2023)
Application Details
Description

Proposed Construction and Operation of An 8 MW Electrolytic Green Hydrogen Production Plant, with Associated Infrastructure Including HGV and Multi Cylinder Pack (MCP) Loading Areas, Vehicle Maintenance Unit, Staff Welfare Facilities and Control Room, 11KV Customer Sub-Station, Boundary Fencing, Internal Access Roads, Landscaping, External Lighting and Works.

Council

Bassetlaw

Application Type

Full Planning Permission

Date Received

29 Jun 2023

Date Validated

31 Jul 2023

Decision Date

26 Oct 2023

Location
Address

Land At High Marnham Power Station Power Station Access Fledborough Road High Marnham Nottinghamshire

Coordinates

53.228643800000000, -0.794133200000000

Source: Application UPRN

Quick Info
UID
23/00801/FUL
Reference
23/00801/FUL
Status
Granted
Last Updated
27 Oct 2023