LA08/2023/2859/F

Status: Granted (17 Mar 2025)
Application Details
Description

Upgrades to the existing Water Treatment Works (WTW) at Castor Bay to include a New Water Pumping Station (WPS) with below ground reinforced concrete basement to contain 6 new pumps, with above ground steel portal frame, external cladding and pitched roof. Erection of new High Voltage (HV) building, 2 No. surge vessels, 2 No. valve buildings, 4 No. electrical transformers surrounded by a 3.2 metre high noise barrier fence. Also minor modifications to the existing access road, and the creation of 2 No. new access points. The laying of new pipe infrastructure and associated works.

Council

Armagh Banbridge Craigavon

Application Type

Full

Date Received

20 Oct 2023

Date Validated

24 Oct 2023

Decision Date

17 Mar 2025

Location
Address

Castor Bay Water Treatment Works (WTW) Castor Bay Road, Craigavon, BT679LF

Postcode

BT67 9LF

Coordinates

54.501054952933629, -6.341177046660984

Source: Application Form

Quick Info
UID
677959
Reference
LA08/2023/2859/F
Status
Granted
Last Updated
21 Mar 2025