LA03/2024/0623/DC

Status: Split decision (14 Nov 2024)
Application Details
Description

2.5 km 33kv overhead line and 2km underground cable (Discharge of Condition 6 of planning approval LA03/2021/0758/F reagrding the submission of a Final Construction Environmental Management Plan.)

Council

Antrim Newtownabbey

Application Type

Discharge of Condition

Date Received

14 Aug 2024

Date Validated

14 Aug 2024

Decision Date

14 Nov 2024

Location
Address

Commences 170m south east of 59 Lower Ballyboley Road passing through the townlands of Lismenary, Ballycorr and Ballyeaston and ending at Ballyclare Central substation adjacent to Ballyclare Baptist Church, Ballyclare (Amended address)

Coordinates

54.769480551458905, -5.988001829565704

Source: Lat and Lng

Quick Info
UID
691489
Reference
LA03/2024/0623/DC
Status
Split decision
Last Updated
23 Nov 2024