2.5 km 33kv overhead line and 2km underground cable (Discharge of Condition 6 of planning approval LA03/2021/0758/F reagrding the submission of a Final Construction Environmental Management Plan.)
Council
Antrim Newtownabbey
Application Type
Discharge of Condition
Date Received
14 Aug 2024
Date Validated
14 Aug 2024
Decision Date
14 Nov 2024
Council Website
View on Antrim Newtownabbey websiteLocation
Address
Commences 170m south east of 59 Lower Ballyboley Road passing through the townlands of Lismenary, Ballycorr and Ballyeaston and ending at Ballyclare Central substation adjacent to Ballyclare Baptist Church, Ballyclare (Amended address)
Coordinates
54.769480551458905, -5.988001829565704